⚙️How to install the app?

  1. Log in to your monday account.

  2. Navigate to the upper right corner and click on monday marketplace.

    Ganttly Documentation (1).png
  3. To find our app, search for Ganttly by SolDevelo. You can also find it here: https://monday.com/marketplace/listing/10000968/ganttly .

  4. As an administrator, you can choose to Install app and start using it right away.

  5. While installing, select the workspace and a board you want to add the app to.

  6. If you are not an administrator, you can click on Request to add instead. Once your monday administrator approves the request, the app will be installed.